His discussion in the 2nd video is confusing on estimation. He doesn’t mention that the PMBOK Guide actually has two adjectival levels of description of estimates – ROM & Definitive. He is mixing ROM as a technique for estimating, which it isn’t. The funnel chart in the PMI Approved Guide is completely inaccurate because of the overlap of the three balls.