    FREE . . . for PMP Exam Prep . . . from JamesLHaner.com

    You just created the team. What could you do next?
    Create a WBS and a WBS dictionary
    You just created the WBS and WBS dictionary. What could you do next?
    Create the activity list
    You just created the activity list. What could you do next?
    Create a network diagram
    You just created a network diagram. What could you do next?
    Estimate the resource requirements
    You just estimated the resource requirements. What could you do next?
    Develop the schedule
    You just developed the schedule. What could you do next?
    Determine the critical path
    You just determined the critical path. What could you do next?
    Estimate costs
    You just estimated the costs of the resources needed to complete project activities. What could you
    do next?

    Develop your budget
    You just developed your budget. What could you do next?
    Determine what quality standards, processes and metrics to use
    You just determined quality standards, processes and metrics. What could you do next?
    Determine the team’s roles and responsiblities
    You just determined roles and responsibilities. What could you do next?
    Determine the communications requirements
    You just determined communication requirements. What could you do next?

    FREE . . . for PMP Exam Prep . . . from JamesLHaner.com

    2

    Risk identification, qualitative and quantitative risk analysis and response planning
    You just completed risk identification, qualitative and quantitative risk analysis and response planning.
    What could you do next?
    Go back – and use an iterative approach
    You just went back and did iterations. What could you do next?
    Determine what to purchase
    You just determined what to purchase. What could you do next?
    Prepare procurement documents
    You just finalized “how to execute and control” aspects of all management plans. What could you do
    next?
    Create the process improvement plan
    You just created the process improvement plan. What could you do next?
    Develop the final project management plan and performance measurement baseline
    You just developed the project management plan and performance measurement baseline. What could
    you do next?
    Gain formal approval for your project management plan
    You just gained formal approval for your plan. What could you do next?
    Hold a kick-off meeting
    You just held your kickoff meeting. What could you do next?
    Acquire the project team
    You just developed your project scope statement. What could you do next?
    Determine what approach to use for planning

    #1345
    JLHaner
    Participant

    FREE – PMP Exam Prep – Domain 2: Process . . . JamesLHaner.com
    You just developed your project scope statement. What could you do next?
    Determine what approach to use for planning

    You just created the team. What could you do next? Create a WBS and a WBS dictionary
    You just created the WBS and WBS dictionary. What could you do next?
    Create the activity list

    You just created the activity list. What could you do next? Create a network diagram
    You just created a network diagram. What could you do next? Estimate the resource requirements
    You just estimated the resource requirements. What could you do next? Develop the schedule
    You just developed the schedule. What could you do next? Determine the critical path
    You just determined the critical path. What could you do next?

    Estimate costs
    You just estimated the costs of the resources needed to complete project activities. What could you
    do next?

    Develop your budget
    You just developed your budget. What could you do next? Determine what quality standards, processes
    and metrics to use
    You just determined quality standards, processes and metrics. What could you do next?
    Determine the team’s roles and responsibilities

    You just determined roles and responsibilities. What could you do next? Determine the
    communications requirements
    You just determined communication requirements. What could you do next?

    FREE . . . for PMP Exam Prep . . . from JamesLHaner.com
    Risk identification, qualitative and quantitative risk analysis and response planning

    You just completed risk identification, qualitative and quantitative risk analysis and response
    planning. What could you do next?

    Go back – and use an iterative approach

    You just went back and did iterations. What could you do next? Determine what to purchase
    You just determined what to purchase. What could you do next? Prepare procurement documents
    You just finalized “how to execute and control” aspects of all management plans. What could you do
    next?

    Create the process improvement plan

    You just created the process improvement plan. What could you do next?

    Develop the final project management plan and performance measurement baseline

    You just developed the project management plan and performance measurement baseline. What could you
    do next?

    Gain formal approval for your project management plan

    You just gained formal approval for your plan. What could you do next? Hold a kick-off meeting
    You just held your kickoff meeting. What could you do next? Acquire the project team